How to install jaw crusher or jaw rock crusher

pdf downloadDownload SBM Products Data

Check out these factors before installing jaw crusher:

The Jaw Crusher should be installed in the place avoiding rain and sunlight.
Jaw crusher motor should be installed behind the crusher; the direction of rotation should follow the requirement which cannot be changed.
Jaw Crusher should be installed on the concrete base, there should be a discharge chute in the concrete base, and the angle should exceed 50 º. The base condition can be decided according to the materials and transporting equipment.
the spring before adjust the discharge outlet. After adjusting well, fasten the spring till the working noise of toggle plate and toggle plate seat is at minimum, and the toggle plate doesn’t fall down.
Make a trial run of your jaw crusher
all the bolts are fastened before trial run.
the lubrication before trial run.
the flywheel by hand first, trial-run can only carried out after confirmation that there is no block. There should be no impact, oil leak, shake of flywheel, and looseness of shaft within two hours.
Trial run with loading for ten hours, if the stuff is hard, no above problems and the temperature of bearing doesn’t exceed 70℃, the machine can be put into operation.

starting up, make these preparations.
Check the lubrication. (The manufacturer just oils the machine for trial run.
whether all the parts are fastened.
the belts, if the belts or flywheel has been dirtied by oil, clean it immediately.
The Jaw Crusher should be started up without loading, make sure that there is no stuff between mobile jaw plate and stationary jaw plate.

When the stuff is very hard, the max feed size should less than 2/3 of the opening width.
The Jaw Crusher should be started up without loading.
It's okay. Just start up your jaw crusher.
If you find anything wrong after starting up jaw crusher, stop the machine and check out carefully.